Funding entity Endesa Generación-Unelco
The aim of this project is the model up date of La Palma power system including the new diesel generators 14 and 15 at Guinchos power station. In addition, steady-state and dynamic studies will be performed. Steady state studies determine the power flows and the bu voltages. The dynamic studies evaluate the dynamic response of generators in case of generator tripping and network faults.