Studies of the Castelnou combined clyce power plant

L. Rouco C. Domingo P. García-González

January 2005 - March 2005

Funding entity Initec Energía


The aim of this project is the development of two studies of the Castelnou combined clyce power plant: stability and main transformer inrush. The stability study will evaluate the plant performance in case of a fault or in case the tripping of a unit of the plant. The main transformer inrush study will determine the inrush current of the step-up transformer when it is connected to the Spanish power network.


    Research topics:

InitecCastelnou