Islanded operation of BP Oil cogeneration plant

L. Rouco E. Lobato

July 2008 - April 2009

Funding entity Iberdrola Ingeniería y Construcción


This project is aimed at determining the conditions for the islanded operation of the cogeneration plant of the BP Oil refinery in Castellon. We determine the conditions that require the islanded operation and the load to be shed so the plant is supplying the loads at stable frequency and voltage.


    Research topics:
  • *Stability: large disturbance stability, tuning of frequency loadshedding schemes, excitation control, small disturbance stability, tuning of power system stabilizers, identification of AVR and governor models