Funding entity Dimetronic Signals
Participated by Ferrocarrils de la Generalitat de Catalunya
The objective of this project is the validation of the expected capacity increased in the previous theoretical study due to the modification of the signalling system in Plaza de Catalunya, Provenza, Gracia and Sant Cugat. This validation is done by means of real measurements registered during commercial services, comparing the critical interval time between trains.
In this project the new timetable of 32 trains/hours is tested during 2 nocturnal tests sessions without passengers, and times and delays are analysed to validate its robustness. In addition, new Plaza de Catalunya track designs and analysed to verify the required capacity of 40 trains/h.
FGCval
Legal notice | Cookies policy | Privacy policy
Calle de Santa Cruz de Marcenado, 26 - 28015 Madrid, Spain - Tel: (+34) 91 542 28 00
We use our own and third-party cookies to improve the functionality of our website and the quality of our service, by analyzing your browsing habits. I accept this site's cookies.
|
|